Increase of Capacity Altstetten-Süd/ZH


Referenz Engineering Gleisaufbau Altstetten

Spacer over Text Main

Problem and task



Spacer over Text Main

At the sub-crossing construction "Increase of capacity Altstetten-Süd" in Zurich the bottom plate should - for logitical reasons - be built using two layers. For the upper layer (screed) a type of concrete should be developped with which a conventional reinforcement and connecting reinforcement (or dowelling) to the existing concrete would be unnecessary.


Spacer over Text Main

Requirements to the concrete:


Icon Bullet
Spacer between icon and text
Spacer over Text Main

Element length: 12 m, element width: 70 to 150 cm, max. slope: 6%.

Spacer over Text Main
Icon Bullet
Spacer between icon and text
Spacer over Text Main

Force transmission only over the roughness in the contact surface, no reinforcement.

Spacer over Text Main
Icon Bullet
Spacer between icon and text
Spacer over Text Main

High frost resistance, high durability.

Spacer over Text Main


Spacer over Text Main

Solution



Icon Bullet
Spacer between icon and text
Spacer over Text Main

Development of a shrinkage-optimized binder mixture.

Spacer over Text Main
Icon Bullet
Spacer between icon and text
Spacer over Text Main

Integral development of a concrete formulation with high-efficiency plastic fibers.

Spacer over Text Main
Icon Bullet
Spacer between icon and text
Spacer over Text Main

Definiton of the important material properties and numerical simulation of the material behaviour (shrinkage, cracking).

Spacer over Text Main
Icon Bullet
Spacer between icon and text
Spacer over Text Main

Optimising of the concrete formula and development of an object- and material-specific curing concept.

Spacer over Text Main
Icon Bullet
Spacer between icon and text
Spacer over Text Main

Tests in advance and attendance during the realization.

Spacer over Text Main


Spacer over Text Main

Judgement



Spacer over Text Main

The project was finished sucessfully and on time. The suggested solution proved its worth both from the technical and the economical angle.








Facts





Spacer over text Side

Duration of the product:
January to July 2002.




Spacer over text Side

Building owner:
SBB




Spacer over text Side

Client:
Locher AG, Zurich










Icon Print
Spacer between icon and text
Spacer over text Side
Show print version

Icon Generate PDF
Spacer between icon and text
Spacer over Text Main
Generate PDF
Spacer over text Side
Top
Spacer between icon and text
Icon Top



Webdesign by Screenlight
Spacer between icon and text

-

Spacer between icon and text
Content Management by CMS Toolpark pc3